FY2022

Department AIRPORT

A3471

Project #

Contact Michael Tharp

Project Name Runway 12/30 Threshold Displacement/Relocation

Type One Phase

Useful Life 20 years

GRANTEE FAA

PLAN Airport Master Plan

Category Airport

MATCH % 10%

TIF DISTRICT None

Priority Critical (1)

Total Project Cost: $397,250

Description Runway 12 Threshold Displacement - Runway 30 Threshold Relocation

Status Active

Justification The Airport Master Plan completed in 2016 identifies a threshold displacement on Runway 12 of 500 feet to minimize the number of potential obstructions to the Runway 12 approach. The plan mitigated the impactes to Runway 12/30 by adding length to the Runway 30 end that is available for takeoff but not for landings.

Expenditures

Total

2021

2022

2023

2024

2025

PLANNING/DESIGN CONSTRUCTION

72,250

72,250

325,000

325,000

72,250

325,000

397,250

Total

Funding Sources AIRPORT FUND FEDERAL GRANTS

Total

2021

2022

2023

2024

2025

7,225

32,500

39,725

65,025

292,500

357,525

72,250

325,000

397,250

Total

Budget Impact/Other This project will add minor paving maintenance expenses due to the added pavement at Runway 30.

Department AIRPORT

A3473

Project #

Contact Michael Tharp

Project Name Airport Apron Expansion

Type One Phase

Useful Life 20 years

GRANTEE FAA

PLAN Airport Master Plan

Category Airport

MATCH % 10%

TIF DISTRICT None

Priority Essential (2)

Total Project Cost: $1,250,000

Description This project adds additonal apron space for aircraft parking.

Status Active

Justification Larger aircraft utilizing the airport require hard surface parking. Our exisiting ramp is too small based on FAA formulas for operations and parking. This project provides additional parking space to support those aircraft types.

Expenditures

Total

2021

2022

2023

2024

2025

PLANNING/DESIGN CONSTRUCTION

375,000

375,000

875,000

875,000

1,250,000

1,250,000

Total

Funding Sources AIRPORT FUND FEDERAL GRANTS

Total

2021

2022

2023

2024

2025

125,000

125,000

1,125,000

1,125,000

1,250,000

1,250,000

Total

Budget Impact/Other The operating impact will be increased costs for snow removal and maintenance due to increased surface pavement. The estimated increase in operating expenditures is less than $10,000.

509

Made with FlippingBook flipbook maker