FY2022

Contact Juli Seydell-Johnson Department PARKS & RECREATION

R4351

Project #

Project Name Recreation Center Improvements

Type Multi-Phase

Useful Life 25 years

GRANTEE NONE

PLAN Facilities Master Plan

Category Recreation

MATCH % NONE

TIF DISTRICT None

Priority Critical (1)

Description This project is planning for renovations for the City's recreation enters: Robert A. Lee (RALRC) and Mercer Pool/Scanlon Gym. Total Project Cost: $1,000,000

Status Active

2022 - Merce/Scanlon: outdoor entry, lighting and parking lot resurfacing; 2023 - Upper Level RALRC: ADA compliant single user public restrooms, ADA compliant offices, door and signage needs. Catering kitchen to be relocated to the Social Hall. 2024 - RALRC: renovate Lower Level locker rooms. 2025 - Mercer/Scanlon: renovate lobby, restrooms, and meeting rooms. Future: Renovate Mercer/Scanlon locker rooms Justification Presently there are critical and public use areas of the recreation facilities do not meet the current ADA standards. Parts of the facilities are still operating from their original design. These improvements will update and bring the facilities into closer compliance with ADA requirements and improve operational efficiencies in their use for both the public and the staff. These recommendations were cited in the 2012 Space Needs Study and Master Plan and the Facility ADA study.

Expenditures

Total

2021

2022

2023

2024

2025

PLANNING/DESIGN CONSTRUCTION ADMINISTRATION

25,000

25,000

50,000

425,000

425,000

850,000

25,000

25,000

50,000

CONTINGENCY

25,000

25,000

50,000

500,000

500,000

1,000,000

Total

Funding Sources GO BONDS-GENERAL PURPOSE

Total

2021

2022

2023

2024

2025

500,000

500,000

1,000,000

500,000

500,000

1,000,000

Total

Budget Impact/Other This project would reduce maintenance and repair expenditures due to the replacement of older infrastructure. The estimated annual reduced operating expenditures is less than $10,000 per year.