Contact Scott Sovers Department PUBLIC WORKS
S3961
Project #
Project Name Foster Road Elevation
Type Multi-Phase
Useful Life 30 Years
GRANTEE NONE
PLAN None
Category Street Operations
MATCH % NONE
TIF DISTRICT None
Priority Critical (1)
Description The initial phase of this project will be to develop functional design plans for the elevation of Foster Road from No Name Street to Dubuque Street. Justification Currently Foster Road is the single means of access for the Peninsula neighborhood. When the Iowa River reaches major flood stages, portions of Foster Road between No Name Street and Dubuque Street become inundated, thus requiring neighborhoods to be evacuated. The intent of this project is to elevate Foster Road above historic flood levels to maintain access to the Peninsula area. Total Project Cost: $75,000 Status Active
Expenditures
Total
2021
2022
2023
2024
2025
PLANNING/DESIGN
75,000
75,000
75,000
75,000
Total
Funding Sources GENERAL FUND
Total
2021
2022
2023
2024
2025
75,000
75,000
75,000
75,000
Total
Budget Impact/Other This project will not have an impact on the operating budget.