FY2022

Contact Jason Havel Department PUBLIC WORKS

S3965

Project #

Project Name Fairchild Street Reconstruction

Type One Phase

Useful Life 50 years

GRANTEE NONE

PLAN None

Category Street Operations

MATCH % NONE

TIF DISTRICT None

Priority Essential (2)

Description This project includes the reconstruction of two blocks of brick street along Fairchild Street from Clinton Street to Linn Street. Total Project Cost: $1,400,000

Status Active

Justification The pavement condition in these areas is poor, and several areas have utilities that are in need of repair/replacement, which is contributing to the deterioration of the street.

Expenditures

Total

2021

2022

2023

2024

2025

PLANNING/DESIGN CONSTRUCTION

100,000

100,000

1,100,000

1,100,000

INSPECTION

50,000

50,000

ADMINISTRATION CONTINGENCY

50,000

50,000

100,000

100,000

100,000

1,300,000

1,400,000

Total

Funding Sources

Total

2021

2022

2023

2024

2025

GO BONDS-ESSENTIAL PURPOSE

1,400,000

1,400,000

1,400,000

1,400,000

Total

Budget Impact/Other Estimated savings in operating expenses are less than $10,000 per year.

This serves as a declaration of official intent under Treasury Regulation 1.150-2 that it is reasonably expected that capital expenditures will be made in respect of the above-described project, such expenditures to be advanced from the Wastewater fund, and the City reasonably expects to reimburse all or a portion of the expenditures with the proceeds of bonds, notes or other indebtedness to be issued or incurred by the City in the future.

575

Made with FlippingBook flipbook maker