FY2023 Adopted Budget

Project Summary By Name

AIRPORT

Department

A3447

Project #

Michael Tharp

Contact

Project Name Airport Parking Lot Expansion

One Phase

Type

20 years

Useful Life

GRANTEE IDOT

PLAN None

Airport

Category

MATCH % 20%

TIF DISTRICT None

Efficiency Improvement (3)

Priority

Description Expand airport parking to construct additional spaces around the airport beacon circle. Project would create 15-20 additional spaces. Total Project Cost: $75,000 Status

Active

Justification Airport parking is becoming frequently more full as the airport has become better utilized by charter passenger customers and other groups and employees using the airport. There are now weekly occurances where the parking is 100% full.

Expenditures

Total

2022

2023

2024

2025

2026

PLANNING/DESIGN

10,000

10,000

CONSTRUCTION

65,000

65,000

75,000

75,000

Total

Prior

Funding Sources

Total

2022

2023

2024

2025

2026

12,000

OTHER STATE GRANTS

63,000

63,000

63,000

63,000

Total

Total

Budget Impact/Other There will be a minor increase in pavement maintenance costs for recurring maintenance/striping and snow and ice removal.

AIRPORT

Department

A3462

Project #

Michael Tharp

Contact

Project Name Hangar A Door Replacement

Multi-Phase

Type

50 years

Useful Life

GRANTEE IDOT

PLAN None

Airport

Category

MATCH % 30%

TIF DISTRICT None

Essential (2)

Priority

Description Hangar A door replacement; Hangar A has 10 doors to be replaced. Phase 1 and 2 will replace approximately 4 doors each pending bids. Phase 3 is a future project. Justification Hangar building A contains doors that are manual operation on a pulley/counterweight system. These doors are becoming difficult for some tenants to operate, and are frequently the last hangars to be rented when openings occur. Proposal is to replace the doors with electric motor doors which would enhance the appeal of the hangar and allow for rates to be in line with other hangars of similar size with motorized doors. Total Project Cost: $94,000 Status Active

Expenditures

Total

2022

2023

2024

2025

2026

PLANNING/DESIGN

19,000

19,000

CONSTRUCTION

75,000

75,000

94,000

94,000

Total

Funding Sources

Total

2022

2023

2024

2025

2026

AIRPORT FUND

19,000

19,000

OTHER STATE GRANTS

75,000

75,000

94,000

94,000

Total

Budget Impact/Other Minor decrease in operating expenses due to decreased maintenance and repair expenses on the doors. The decrease in operating expenditures is less than $10,000.