FY2023 Adopted Budget
PARKS & RECREATION
Department
R4359
Project #
Juli Seydell-Johnson
Contact
Project Name Kiwanis Park Playground & Shelter Renovation
One Phase
Type
20 years
Useful Life
GRANTEE NONE
PLAN Park Master Plan
Parks Maintenance
Category
MATCH % NONE
TIF DISTRICT None
Essential (2)
Priority
Description Renovate Nature Play Area, replace shelter, add accessible paths and opportunities for creek access at Kiwanis Park. Total Project Cost: $425,000
Active
Status
Justification Kiwanis playground was installed in 1999. The 2017 Park Master Plan prioritizes renovation of the nature play area, shelter and accessible paths.
Expenditures
Total
2022
2023
2024
2025
2026
PLANNING/DESIGN
30,000
30,000
CONSTRUCTION
355,000
355,000
INSPECTION
5,000
5,000
ADMINISTRATION
5,000
5,000
CONTINGENCY
30,000
30,000
425,000
425,000
Total
Funding Sources
Total
2022
2023
2024
2025
2026
GO BONDS-ESSENTIAL PURPOSE
425,000
425,000
425,000
425,000
Total
Budget Impact/Other No impact on operating budget as these are replacements for current facilities.
557