FY2023 Adopted Budget
PUBLIC WORKS
Department
L3344
Project #
Jen Jordan
Contact
Project Name ACM Landfill Gas Infrastructure Expansion
One Phase
Type
30 Years
Useful Life
GRANTEE NONE
PLAN None
Landfill
Category
MATCH % NONE
TIF DISTRICT None
Critical (1)
Priority
Description The project consists of installing six leachate extraction pneumatic pumps, air supply lines and leachate drainage lines in gas wells in two old unlined areas of the landfill which have seen leachate migration impacts. Justification This project is required to be complete by December 21, 2022, to meet the regulatory requirements with the Corrective Action Plan negotiated with the Iowa Department of Natural Resources as part of the Assessment of Corrective Measures (ACM). The ACM was negotiated in summer 2021. Total Project Cost: $198,800 Status Active
Expenditures
Total
2022
2023
2024
2025
2026
PLANNING/DESIGN
30,000
30,000
CONSTRUCTION
142,600
142,600
INSPECTION
6,000
6,000
ADMINISTRATION
6,000
6,000
CONTINGENCY
14,200
14,200
198,800
198,800
Total
Funding Sources
Total
2022
2023
2024
2025
2026
LANDFILL FUND
198,800
198,800
198,800
198,800
Total
Budget Impact/Other These updates will continue to reduce potential long-term liability for groundwater contamination and reduce long-term groundwater testing expenses. The estimated decrease in operating expenditures is less than $10,000 per year.
582