FY2023 Adopted Budget

PUBLIC WORKS

Department

P3953

Project #

Ron Knoche

Contact

Project Name Equipment Maintenance Facility replacement

One Phase

Type

40 Years

Useful Life

GRANTEE NONE

PLAN Facilities Master Plan

Equipment

Category

MATCH % NONE

TIF DISTRICT None

Essential (2)

Priority

Description Construct a new Equipment Maintenance Facility on the public works campus to replace the old and dated facility at the corner of Highways 1 & 6. Total Project Cost: $12,000,000 Status Active

Justification The current Equipment Maintenance Facility is outdated, inefficient, and a poor working environment for the employees.

Expenditures

Total

2022

2023

2024

2025

2026

PLANNING/DESIGN

1,000,000

1,000,000

CONSTRUCTION

11,000,000

11,000,000

1,000,000

11,000,000

12,000,000

Total

Funding Sources

Total

2022

2023

2024

2025

2026

EQUIPMENT FUND

1,000,000

3,500,000

4,500,000

FACILITY REPLACEMENT RESERVE GO BONDS-GENERAL PURPOSE

4,000,000

4,000,000

700,000

700,000

LANDFILL FUND

500,000

500,000

REFUSE COLLECTION FUND

250,000

250,000

STORMWATER FUND

250,000

250,000

WASTEWATER FUND

1,000,000

1,000,000

WATER FUND

800,000

800,000

1,000,000

11,000,000

12,000,000

Total

Budget Impact/Other A new facility will be more energy efficient which will save costs on utilities; however, a newer facility will add square footage and increase insurance, cleaning, and similar expenses. The estimated annual increase in operating expenditures is $50,000 to $100,000 per year.