FY2023 Adopted Budget

PUBLIC WORKS

Department

S3946

Project #

Scott Sovers

Contact

Project Name Court Street Reconstruction

One Phase

Type

50 years

Useful Life

GRANTEE NONE

PLAN None

Street Operations

Category

MATCH % NONE

TIF DISTRICT None

Essential (2)

Priority

Total Project Cost: $7,500,000

Description This project will reconstruct Court Street from Muscatine Avenue to 1st Avenue.

Active

Status

Justification Court Street is an important collector street that connects the east side of Iowa City to the Downtown area. The project will replace aging street and sidewalk pavement that is in poor condition and upgrade public utilities as needed.

Expenditures

Total

2022

2023

2024

2025

2026

Prior

PLANNING/DESIGN

150,000

150,000

900,000

CONSTRUCTION

5,600,000

5,600,000

Total

INSPECTION

200,000

200,000

ADMINISTRATION

150,000

150,000

CONTINGENCY

500,000

500,000

150,000

6,450,000

6,600,000

Total

Prior

Funding Sources

Total

2022

2023

2024

2025

2026

900,000

GO BONDS-ESSENTIAL PURPOSE

6,600,000

6,600,000

Total

6,600,000

6,600,000

Total

Budget Impact/Other Replacing aged infrastructure will lower the City's operating expenditures through decreased maintenance costs. The estimated decrease in operating expenses is less than $10,000 per year. This serves as a declaration of official intent under Treasury Regulation 1.150-2 that it is reasonably expected that capital expenditures will be made in respect of the above-described project, such expenditures to be advanced from the Capital Projects fund, and the City reasonably expects to reimburse all or a portion of the expenditures with the proceeds of bonds, notes or other indebtedness to be issued or incurred by the City in the future.