FY2023 Adopted Budget

PUBLIC WORKS

Department

S3956

Project #

Jason Havel

Contact

Project Name Gilbert Street Bridge Replacement

One Phase

Type

50 years

Useful Life

GRANTEE IDOT

PLAN None

Street Operations

Category

MATCH % 60%

TIF DISTRICT None

Critical (1)

Priority

Description This project will replace the existing Gilbert Street bridge over Ralston Creek. In addition, the project will include removal and replacement of slope protection, sidewalk, storm sewer and street pavement, and other related work. Justification The 2017 Biennial Bridge Inspection Program identified advanced deterioration of the deck and super structure on the Gilbert Street bridge. The Program recommended the bridge be scheduled for significant repairs or replacement. Total Project Cost: $3,300,000 Status Active

Expenditures

Total

2022

2023

2024

2025

2026

Prior

CONSTRUCTION

2,600,000

2,600,000

175,000

INSPECTION

150,000

150,000

Total

ADMINISTRATION

75,000

75,000

CONTINGENCY

300,000

300,000

3,125,000

3,125,000

Total

Funding Sources

Total

2022

2023

2024

2025

2026

FEDERAL GRANTS

1,000,000

1,000,000

GO BONDS-ESSENTIAL PURPOSE

2,300,000

2,300,000

3,300,000

3,300,000

Total

Budget Impact/Other Replacing aged infrastructure will lower the City's operating expenditures through decreased maintenance costs. The estimated decrease in operating expenses is less than $10,000 per year. This serves as a declaration of official intent under Treasury Regulation 1.150-2 that it is reasonably expected that capital expenditures will be made in respect of the above-described project, such expenditures to be advanced from the Capital Projects fund, and the City reasonably expects to reimburse all or a portion of the expenditures with the proceeds of bonds, notes or other indebtedness to be issued or incurred by the City in the future.