FY2024 Proposed Budget
Capital Improvement Plan 2023-2027 City of Iowa City, Iowa
2023 2027 thru
Department AIRPORT
Contact Michael Tharp
Type One Phase
A3475
Project #
Useful Life 20 years Category Airport
Project Name Runway 12/30 Pavement Repairs
Priority Critical (1)
MATCH % 10% GRANTEE FAA
PLAN Airport Master Plan
TIF DISTRICT None
Status Active
Total Project Cost: $167,000
Description Runway joint and crack sealing and pavement repairs to the west half of runway 12/30
Justification Project would route and seal joints as well as perform any panel repairs as needed to maintain the runway.
Expenditures
Total
2023
2024
2025
2026
2027
20,000 147,000 167,000
20,000 147,000 167,000
PLANNING/DESIGN CONSTRUCTION
Total
Funding Sources
Total
2023
2024
2025
2026
2027
17,000 150,000 167,000
17,000 150,000 167,000
AIRPORT FUND
FEDERAL GRANTS
Total
Budget Impact/Other Extends the life of the runway and reduces annual budget needs for short term maintenance