FY2024 Proposed Budget
Capital Improvement Plan 2023-2027 City of Iowa City, Iowa
2023 2027 thru
Department PUBLIC WORKS
Contact Jen Jordan
Type One Phase
L3347
Project #
Useful Life 10 years Category Landfill
Project Name Compost Turner
Priority Efficiency Improvement (3)
MATCH % GRANTEE
TIF DISTRICT PLAN
Status Active
Total Project Cost: $300,000
Description This machine would be used to more efficiently turn compost windrows.
Justification Compost is currently turned by an endloader, which takes approximately 40 hours per month. A turner would reduce this by about half; staff would have time to turn the piles more frequently. Increased turning reduces processing time, allowing more material to be processed in the same amount of time or less. This results in increased diversion from the landfill and the additional compost would yield additional revenue.
Expenditures
Total
2023
2024
2025
2026
2027
300,000 300,000
300,000 300,000
OTHER
Total
Funding Sources LANDFILL FUND
Total
2023
2024
2025
2026
2027
250,000 50,000 300,000
250,000 50,000 300,000
OTHER STATE GRANTS
Total
Budget Impact/Other Quicker processing would allow for more material to be processes, resulting in additional compost for sale. Assuming a 25% increase would result in approximately $10,000 additional revenue per year. Grant assistance is feasible for this purchase.