FY2024 Proposed Budget
Capital Improvement Plan 2023-2027 City of Iowa City, Iowa
2023 2027 thru
Department PUBLIC WORKS
Contact Ron Knoche
Type One Phase
P3953
Project #
Useful Life 40 Years
Project Name Equipment Maintenance Facility replacement
Priority Essential (2) Category Equipment
MATCH % NONE GRANTEE NONE
PLAN Facilities Master Plan
TIF DISTRICT None
Status Active
Description Construct a new Equipment Maintenance Facility on the public works campus to replace the old and dated facility at the corner of Highways 1 & 6. Total Project Cost: $13,000,000
Justification The current Equipment Maintenance Facility is outdated, inefficient, and a poor working environment for the employees.
Expenditures
Total
2023
2024
2025
2026
2027
1,000,000
1,000,000 12,000,000 13,000,000
PLANNING/DESIGN CONSTRUCTION
12,000,000 12,000,000
1,000,000
Total
Funding Sources EQUIPMENT FUND
Total
2023
2024
2025
2026
2027
1,000,000
7,500,000 1,000,000
8,500,000 1,000,000
FACILITY REPLACEMENT RESERVE GO BONDS-GENERAL PURPOSE
700,000
700,000
500,000 250,000 250,000
500,000 250,000 250,000
LANDFILL FUND
REFUSE COLLECTION FUND
STORMWATER FUND WASTEWATER FUND
1,000,000
1,000,000
800,000
800,000
WATER FUND
1,000,000
12,000,000
13,000,000
Total
Budget Impact/Other A new facility will be more energy efficient which will save costs on utilities; however, a newer facility will add square footage and increase insurance, cleaning, and similar expenses. The estimated annual increase in operating expenditures is $50,000 to $100,000 per year. This serves as a declaration of official intent under Treasury Regulation 1.150-2 that it is reasonably expected that capital expenditures will be made in respect of the above-described project, such expenditures to be advanced from the Capital Projects fund, and the City reasonably expects to reimburse all or a portion of the expenditures with the proceeds of bonds, notes or other indebtedness to be issued or incurred by the City in the future.