FY2024 Proposed Budget
Capital Improvement Plan 2023-2027 City of Iowa City, Iowa
2023 2027 thru
Department PUBLIC WORKS
Contact Scott Sovers
Type One Phase
S3983
Project #
Useful Life 50
Project Name Iowa Avenue Improvements
Category Street Operations
Priority Essential (2)
MATCH % GRANTEE
TIF DISTRICT PLAN
Status Active
Description This corridor is a part of the downtwon streetscape master plan. The scope of thie project is the reconstruction of Iowa Avenue from Clinton Street to Gilbert Street. The project also includes replacement of sidewalks and curb ramps, utility upgrades and streetscape amenities. Total Project Cost: $800,000
Justification Iowa Avenue is an important corridor within the downtown area that is lined with the retail on the south side and the University of Iowa Campus on the north. The public infrastructure and streestcape amenities are starting to show signs of detoration and are in need replacement. Addtionally, the electrical system is in need of upgrading to provide adequate power during festivals and events.
Expenditures CONSTRUCTION
Total
2023
2024
2025
2026
2027
800,000 800,000
800,000 800,000
Total
Funding Sources
Total
2023
2024
2025
2026
2027
800,000
800,000
GO BONDS-ESSENTIAL PURPOSE
800,000
800,000
Total
Budget Impact/Other This project is replacing existing infrastructure and should reduce future street maintenance costs. The anticipated annual savings is less than $10,000 per year. This serves as a declaration of official intent under Treasury Regulation 1.150-2 that it is reasonably expected that capital expenditures will be made in respect of the above-described project, such expenditures to be advanced from the Capital Projects fund, and the City reasonably expects to reimburse all or a portion of the expenditures with the proceeds of bonds, notes or other indebtedness to be issued or incurred by the City in the future.