FY2024 Proposed Budget
Capital Improvement Plan 2023-2027 City of Iowa City, Iowa
2023 2027 thru
Department PUBLIC WORKS
Contact Jonathan Durst
Type One Phase
W3332
Project #
Useful Life 40 Years
Project Name Peninsual Well Field Antenna
Category Water Operations
Priority Efficiency Improvement (3)
MATCH % NONE GRANTEE NONE
TIF DISTRICT None PLAN None
Status Active
Description Install a new antenna at the Rocky Shore Dr. lift station by Crandic Park and decommission the antenna at the N. Dodge St. HyVee. Total Project Cost: $200,000
Justification The Peninsula Well Field is integrated with the Water Treatment Plant SCADA system. The well field communication is via radio to the HyVee antenna and then fiber from the antenna to the Water Plant. Resilient and timely communication with the Peninsula Well Field is necessary to effectively monitor raw water production during all weather events. Both the existing and proposed sites have backup power generation. The installation of reliable fiber to the Rocky Shore Dr. lift station is anticipated to occur with S3958 - Park Rd Reconstruction in 2025.
Expenditures
Total
2023
2024
2025
2026
2027
40,000 160,000 200,000
40,000 160,000 200,000
PLANNING/DESIGN CONSTRUCTION
Total
Funding Sources
Total
2023
2024
2025
2026
2027
200,000 200,000
200,000 200,000
WATER FUND
Total
Budget Impact/Other This project will have a neutral impact on the operating budget as it is the replacement of existing infrastructure.