FY24 Adopted Budget
Capital Improvement Plan 2023-2027 City of Iowa City, Iowa
2023 2027 thru
Department PARKS & RECREATION
Contact Juli Seydell-Johnson
Type One Phase
R4346
Project #
Useful Life 20 years
Project Name Palisades or Stone Bridge Park Development
Category Parks Maintenance
Priority Essential (2)
MATCH % NONE GRANTEE NONE
PLAN Park Master Plan
TIF DISTRICT None
Status Active
Description Funding to develop a new neighborhood park in an emerging or underserved location. The City owns several parcels designated for parks and developments are completed. Total Project Cost: $525,000
Justification The 2017 Park Master plan points to a districts with deficiencies in park land. This project will be designed to develop a new neighborhood park in a growing or underserved neighborhood as the opportunity becomes available.
Expenditures
Total
2023
2024
2025
2026
2027
30,000 200,000
30,000 225,000
60,000 425,000 10,000 10,000 20,000 525,000
PLANNING/DESIGN CONSTRUCTION
5,000 5,000
5,000 5,000
INSPECTION
ADMINISTRATION CONTINGENCY
10,000 250,000
10,000 275,000
Total
Funding Sources GENERAL FUND
Total
2023
2024
2025
2026
2027
250,000 250,000
275,000 275,000
525,000 525,000
Total
Budget Impact/Other This project will increase operating expenditures due to the addition of new park amenities and finished park land. The estimated increase in operating expenditures is $20,000 per year.