FY24 Adopted Budget
Capital Improvement Plan 2023-2027 City of Iowa City, Iowa
2023 2027 thru
Department PARKS & RECREATION
Contact Juli Seydell-Johnson
Type One Phase
R4381
Project #
Useful Life 20 years
Project Name Event Facility Improvements
Category Government Buildings
Priority Essential (2)
MATCH % NONE GRANTEE NONE
TIF DISTRICT None PLAN None
Status Active
Description On-going repairs and improvements at Terry Trueblood Lodge, Terry Trueblood concession building, Ashton House Event Facility and Riverside Festival Stage. 2023 Renovate Riverside Festival Stage. FY24- ADA update to Ashton House remove and replace back stair from upper floor. Critical repairs needed to Riverside Festival Stage. Total Project Cost: $1,000,000
Justification These facilities are maintained for city events and private event rentals. Renovations are needed as they buildings age.
Prior
Expenditures
Total
2023
2024
2025
2026
2027
75,000 700,000
10,000 135,000
85,000 835,000
50,000
PLANNING/DESIGN CONSTRUCTION ADMINISTRATION
Total
5,000
5,000
20,000 800,000
5,000
25,000 950,000
CONTINGENCY
150,000
Total
Prior
Funding Sources GENERAL FUND GO BONDS-GENERAL PURPOSE OTHER STATE GRANTS
Total
2023
2024
2025
2026
2027
150,000
150,000 300,000 500,000 950,000
50,000
300,000
Total
500,000 800,000
150,000
Total
Budget Impact/Other This project should have a minimal impact on the annual operating budget.
This serves as a declaration of official intent under Treasury Regulation 1.150-2 that it is reasonably expected that capital expenditures will be made in respect of the above-described project, such expenditures to be advanced from the Capital Projects fund, and the City reasonably expects to reimburse all or a portion of the expenditures with the proceeds of bonds, notes or other indebtedness to be issued or incurred by the City in the future.