Final FY25 Adopted Budget

2024 2028 thru

Capital Improvement Plan 2024-2028 City of Iowa City, Iowa

PUBLIC WORKS

Department

Contact Jason Havel

Annual

Type

S3910

Project #

50 years

Useful Life

Project Name Annual Bridge Maintenance & Repair

Street Operations

Category

GRANTEE NONE

PLAN None

Critical (1)

Priority

MATCH % NONE

TIF DISTRICT None

Active

Status

Total Project Cost: $3,150,000

Description This provides for the biennial inspection and preservation of Iowa City's bridges including major repairs and restoration.

Justification Repairs to bridge components that have deteriorated because of age or have been damaged from vehicular collisions or other factors, are necessary to provide safe structures for motorists and pedestrians. The budget amount is higher than past years, as necessary repairs have exceeded available funding. Currently, there is a backlog of repairs that need to be completed.

Prior

Expenditures

Total

2024

2025

2026

2027

2028

PLANNING/DESIGN

50,000

25,000

25,000

25,000

35,000

160,000

1,550,000

CONSTRUCTION

300,000

225,000

225,000

225,000

225,000

1,200,000

Total

INSPECTION

15,000

15,000

15,000

15,000

15,000

75,000

ADMINISTRATION

35,000

35,000

35,000

35,000

25,000

165,000

400,000

300,000

300,000

300,000

300,000

1,600,000

Total

Prior

Funding Sources

Total

2024

2025

2026

2027

2028

ROAD USE TAX FUND

400,000

300,000

300,000

300,000

300,000

1,600,000

1,550,000

400,000

300,000

300,000

300,000

300,000

1,600,000

Total

Total

Budget Impact/Other This is a maintenance project, and repairs will require continued regular maintenance. However, completing maintenance on a regular basis should reduce maintenance costs over the life of the bridges.

590

Made with FlippingBook Annual report maker