Final FY25 Adopted Budget
2024 2028 thru
Capital Improvement Plan 2024-2028 City of Iowa City, Iowa
PUBLIC WORKS
Department
Contact Jason Havel
One Phase
Type
S3953
Project #
30 Years
Useful Life
Project Name Market St & Jefferson St Two-Way Conversion
Street Operations
Category
Essential (2)
GRANTEE
PLAN
Priority
Active
MATCH %
TIF DISTRICT
Status
Total Project Cost: $5,000,000
Description Conversion of Market Street and Jefferson Street from one-way to two-way corridors. The project cost includes new traffic signals, pavement markings and signage necessary to implement the conversion. The conversion is intended to generally take place betweenn Madison Street and the eastern termini of the one-way streets - exact limits subject to further evaluation.This project will also add electrical outlets to each of the pedestrian level light poles on Linn Street from Jefferson Street to Bloomington Street.
Justification The feasibility of the project was initially evaluated as a part of the Downtown Iowa City Traffic Modeling Study completed in 2015.
Expenditures
Total
2024
2025
2026
2027
2028
PLANNING/DESIGN
400,000
400,000
LAND/ROW ACQUISITION
25,000
25,000
CONSTRUCTION
3,825,000
3,825,000
INSPECTION
100,000
100,000
ADMINISTRATION
100,000
100,000
CONTINGENCY
550,000
550,000
425,000
4,575,000
5,000,000
Total
Funding Sources
Total
2024
2025
2026
2027
2028
GO BONDS-ESSENTIAL PURPOSE
5,000,000
5,000,000
5,000,000
5,000,000
Total
Budget Impact/Other Operating budget impacts are assumed to be negliable as the corridors already exist and require rountine maintneance activities. The conversion will only change how the facilities are used by the traveling public. This serves as a declaration of official intent under Treasury Regulation 1.150-2 that it is reasonably expected that capital expenditures will be made in respect of the above-described project, such expenditures to be advanced from the Capital Projects fund, and the City reasonably expects to reimburse all or a portion of the expenditures with the proceeds of bonds, notes or other indebtedness to be issued or incurred by the City in the future.