Final FY25 Adopted Budget

2024 2028 thru

Capital Improvement Plan 2024-2028 City of Iowa City, Iowa

PUBLIC WORKS

Department

Contact Jonathan Durst

One Phase

Type

W3325

Project #

20 years

Useful Life

Project Name Roof Replacements

Water Operations

Category

GRANTEE NONE

PLAN None

Essential (2)

Priority

MATCH % NONE

TIF DISTRICT None

Active

Status

Total Project Cost: $650,000

Description Increase budget based on inflation and previous bid prices. Unfunded projects #62 & 76. Replace the roof membranes on the Water Plant garage, shop, and chemical storage rooms, generator building, well houses, and ground storage reservoir pump houses.

Justification Roof membranes deteriorate over time due to exposure to the elements and inclement weather events. The membranes not replaced in the 2018 project are in need of comprehensive replacement to keep the equipment housed within and out of the elements.

Expenditures

Total

2024

2025

2026

2027

2028

PLANNING/DESIGN

100,000

100,000

CONSTRUCTION

50,000

500,000

550,000

50,000

600,000

650,000

Total

Funding Sources

Total

2024

2025

2026

2027

2028

WATER FUND

50,000

600,000

650,000

50,000

600,000

650,000

Total

Budget Impact/Other Reduction of about $5,000 to $10,000 annually in roof repairs and water mitigation efforts