Final FY25 Adopted Budget

2024 2028 thru

Capital Improvement Plan 2024-2028 City of Iowa City, Iowa

PUBLIC WORKS

Department

Contact Jonathan Durst

One Phase

Type

W3328

Project #

70 years

Useful Life

Project Name Powerhouse Dam Rehabilitation

Water Operations

Category

Critical (1)

GRANTEE

PLAN

Priority

Active

MATCH %

TIF DISTRICT

Status

Total Project Cost: $600,000

Description Repair defects found during an underwater inspection of the Iowa River powerhouse dam located below the pedestrian bridge connecting the Iowa River Power Restaurant to the Peninsula Well Field area.

Justification The powerhouse dam maintains the Iowa River elevation in the tract extending from the Coralville Dam to the powerhouse dam. This pool elevation directly impacts the production of the water treatment facility collector wells #1 and #2 by providing hydrostatic pressure above the well laterals. The dam's failure would also negatively impact the pedestrian bridge and other surrounding infrastructure. The inspection work has been completed. The repair design and construction remain.

Prior

Expenditures

Total

2024

2025

2026

2027

2028

PLANNING/DESIGN

107,050

107,050

225,000

CONSTRUCTION

165,000

165,000

Total

ADMINISTRATION

50,000

50,000

CONTINGENCY

52,950

52,950

375,000

375,000

Total

Prior

Funding Sources

Total

2024

2025

2026

2027

2028

WATER FUND

375,000

375,000

225,000

375,000

375,000

Total

Total

Budget Impact/Other This project will have a neutral impact on the operating budget as it is the replacement of existing infrastructure.