Contact Tim Wilkey Depar tment PUBLIC WORKS
V3180
Pr oject #
Pr oject Name Peninsula Contr ol Panel and Pump Impr ovement
Type One Phase
Useful Life 20 years
MATCH % NONE GRANTEE NONE
TIF DISTRICT None PLAN None
Categor y Wastewater Treatment
Pr ior ity Essential (2)
Description The project includes the replacement of the control panel and aquisistion of a redundent pump. Total Pr oject Cost: $97,500
Status Active
Justification This station was placed in service in 2005 and existing deficiencies in the control panel have caused operational and communication problems.
Expenditur es
Total
2022
2023
2024
2025
2026
2,000
2,000
PLANNING/DESIGN CONSTRUCTION
85,000
85,000
1,000 1,000 8,500
1,000 1,000 8,500
INSPECTION
ADMINISTRATION CONTINGENCY
97,500
97,500
Total
Funding Sour ces WASTEWATER FUND
Total
2022
2023
2024
2025
2026
97,500 97,500
97,500 97,500
Total
Budget Impact/Other The estimated impact on the operating budget is less than $10,000.