2022-2026 Capital Improvement Program.pdf

Contact Darian Nagle-Gamm Depar tment TRANSPORTATION SERVIC

T3023

Pr oject #

Pr oject Name Par king Ramp Automated Par king Equipment

Type Multi-Phase

Useful Life 10 years

MATCH % NONE GRANTEE NONE

TIF DISTRICT None PLAN None

Categor y Parking Operations

Pr ior ity Essential (2)

Total Pr oject Cost: $1,275,000

Description Replacement automated parking equipment in parking ramps.

Status Active

Justification Original equipment installed beginning in 2009. Performance is degrading as equipment is reaching the end of its useful life requiring an increasing amount of staff time to address issues.

Expenditur es EQUIPMENT

Total

2022

2023

2024

2025

2026

Pr ior

1,000,000 1,000,000

1,000,000 1,000,000

275,000

Total

Total

Pr ior

Funding Sour ces

Total

2022

2023

2024

2025

2026

275,000

1,000,000

1,000,000

LANDFILL REPLACEMENT RESERVE

Total

1,000,000

1,000,000

Total

Budget Impact/Other Installing new automated parking equipment at all gated facilities will have a positive effect on the operating budget, reducing the amount of staff time required to attend to malfunctioning equipment. The estimated decrease in operating expenditurs is less than $40,000 per year. Loan payments to the Landfill Replacement Reserve will be approxiamtely $60,000 per year including interest expense for 20 years for a $1 million internal loan.

Contact Darian Nagle-Gamm Depar tment TRANSPORTATION SERVIC

T3025

Pr oject #

Pr oject Name Replacement of LED fixtur es in Par king Facilities

Type One Phase

Useful Life 10 years

MATCH % NONE GRANTEE NONE

TIF DISTRICT None PLAN None

Categor y Parking Operations

Pr ior ity Essential (2)

Description Project to replace all LED fixtures in the Court Street Transportation Center, Capitol Street ramp, Dubuque Street ramp, Tower Place ramp, Chauncey Swan Ramp, and fixtures in other facilities as they age out of production. Justification LED technologies have evolved since our early adoption in our parking facilities nearly a decade ago. Many of the early-style fixtures need to be replaced. During 2021 the fixtures in the Court Street Transportation Center were replaced. This project will allow the replacements of the Capitol Street and Dubuque Street facilities in 2022, and Tower Place and Chauncey Swan facilities in 2023. Total Pr oject Cost: $400,000 Status Active

Expenditur es CONSTRUCTION

Total

2022

2023

2024

2025

2026

200,000 200,000

200,000 200,000

400,000 400,000

Total

Funding Sour ces PARKING FUND

Total

2022

2023

2024

2025

2026

200,000 200,000

200,000 200,000

400,000 400,000

Total

Budget Impact/Other It will cost approximately $10,000 in staff time to replace all fixtures in the Capitol Street facility. The impact on the operating budget is negligible.