2022-2026 Capital Improvement Program.pdf
Contact Juli Seydell-Johnson Depar tment PARKS & RECREATION
R4370
Pr oject #
Pr oject Name Rober t A. Lee Recr eation Center Pool Filter & HVAC
Type One Phase
Useful Life 25 years
MATCH % NONE GRANTEE NONE
PLAN Facilities Master Plan
Categor y Government Buildings
TIF DISTRICT None
Pr ior ity Essential (2)
Description This project would include the replacement of the existing pool filters, the addition of a UV system, and a new pool dehumidification system at the Robert A. Lee Recreation Center swimming pool. Justification The current filters are past there life expectancy and are contributing to water quality issues. The dehumidification system will help with pool comfort level and air quality. The UV system is an additional disinfectant for pool water and standard for new pools and pool renovations. Total Pr oject Cost: $700,000 Status Active
Expenditur es CONSTRUCTION CONTINGENCY
Total
2022
2023
2024
2025
2026
Pr ior
600,000 40,000 640,000
600,000 40,000 640,000
60,000
Total
Total
Funding Sour ces GO BONDS-GENERAL PURPOSE
Total
2022
2023
2024
2025
2026
700,000
700,000
700,000
700,000
Total
Budget Impact/Other Operating costs should decrease slightly due to better monitoring of pool chemicals and water use from new equipment and software. Expected annual savings is less than $10,000 per year. This serves as a declaration of official intent under Treasury Regulation 1.150-2 that it is reasonably expected that capital expenditures will be made in respect of the above-described project, such expenditures to be advanced from the Capital Projects fund, and the City reasonably expects to reimburse all or a portion of the expenditures with the proceeds of bonds, notes or other indebtedness to be issued or incurred by the City in the future.