2022-2026 Capital Improvement Program.pdf
Contact Tim Wilkey Depar tment PUBLIC WORKS
V3154
Pr oject #
Pr oject Name Hawkeye Lift Station Rehabilitation
Type One Phase
Useful Life 20 years
MATCH % NONE GRANTEE NONE
TIF DISTRICT None PLAN None
Categor y Wastewater Treatment
Pr ior ity Essential (2)
Description Rehabilitation includes demolishing the existing building, converting the station to a wet-well valve vault with surface hatches for pump access, basket screening, new standby generator, replace 20 year old pump, new controls, valve vault with bypass capacity, new security fence, landscaping and access road improvements. The station would be plumbed for future expansion, but would not include additional pumps. Justification Hawkeye lift station is 50 years old with an aging building, a generator that can no longer be serviced, a deep drywell requiring an elevator and an existing pump that is 20 years old and a replacement pump only 2 years old. Major portions of the station have outlived their useful life and need replacement. Total Pr oject Cost: $1,025,000 Status Active
Expenditur es
Total
2022
2023
2024
2025
2026
25,000
25,000
PLANNING/DESIGN CONSTRUCTION
1,000,000 1,000,000
1,000,000 1,025,000
25,000
Total
Funding Sour ces WASTEWATER FUND
Total
2022
2023
2024
2025
2026
1,025,000 1,025,000
1,025,000 1,025,000
Total
Budget Impact/Other This project will reduce operating and maintenance cost through the rehabilitation of older equipment. The annual savings is less than $10,000 per year.
607