2022-2026 Capital Improvement Program.pdf

Contact Tim Wilkey Depar tment PUBLIC WORKS

V3157

Pr oject #

Pr oject Name Wastewater Plant Mixer Impr ovements

Type One Phase

Useful Life 20 years

MATCH % NONE GRANTEE NONE

TIF DISTRICT None PLAN None

Categor y Wastewater Treatment

Pr ior ity Essential (2)

Description Install new high efficiency mixers in aeration basin trains 1-4, Cell 9 to improve mixing and reduce energy usage. Includes four new high efficiency mixers, electrical improvements and installation. Justification 2010 project made significant improvements to the aeration basin. Cell 9 was not fitted with a mixer but relied on mixing by compressed air. Mixing by compressed air is not as efficient as using a mechanical mixer. The mixers are high efficiency and a lower horsepower than the current mixers installed in Cells 1, 2, 3, 5, 8, and 10. This will reduce wear and tear on the aeration blowers and reduce our electrical usage and carbon footprint. Total Pr oject Cost: $238,000 Status Active

Expenditur es

Total

2022

2023

2024

2025

2026

15,000 200,000

15,000 200,000

PLANNING/DESIGN CONSTRUCTION

2,000 1,000

2,000 1,000

INSPECTION

ADMINISTRATION CONTINGENCY

20,000 238,000

20,000 238,000

Total

Funding Sour ces WASTEWATER FUND

Total

2022

2023

2024

2025

2026

238,000 238,000

238,000 238,000

Total

Budget Impact/Other This will reduce wear and tear on the aeration blowers, reduce our electrical usage/cost, and reduce out carbon footprint. The estimated annual savings is less than $10,000 per year.