Contact Jen Jordan Department PUBLIC WORKS
L3343
Project #
Project Name Landfill Gas Infrastructure Expansion
Type One Phase
Useful Life 30 Years
GRANTEE NONE
PLAN None
Category Landfill
MATCH % NONE
TIF DISTRICT None
Priority Critical (1)
Description The project connects existing loops of of gas line infrastructure on the south central end of the landfill (around cell FY09) to improve overall flow; extends the gas line infrastructure up and around the perimeter of the current cell, FY18; adds vertical collector wells in the existing FY09; and adds horizontal collector lines in the current FY18 cell to meet regulatory and environmental regulations. Justification Tying two loops of of the existing gas line infrastructure together and extending the gas line will improve overall flow to increase the gas draw to the flare. This will allow for better control of landfill gas and reduce the possibility of uncontrolled gas blow-outs in the garbage or dirt cover, reducing potential odor issues and environmental and regulatory liability. Total Project Cost: $792,000 Status Active
Expenditures
Total
2021
2022
2023
2024
2025
PLANNING/DESIGN CONSTRUCTION
62,000
62,000
580,000
580,000
INSPECTION
31,000
31,000
ADMINISTRATION CONTINGENCY
31,000
31,000
88,000
88,000
792,000
792,000
Total
Funding Sources
Total
2021
2022
2023
2024
2025
LANDFILL REPLACEMENT RESERVE
792,000
792,000
792,000
792,000
Total
Budget Impact/Other This project will increase operating costs due to the expansion of infrastructure. The estimated increase in operating expenditures is less than $10,000 per year.