FY2022

Contact Joe Welter Department PUBLIC WORKS

V3155

Project #

Project Name Rohret South Sewer

Type One Phase

Useful Life 50 years

GRANTEE NONE

PLAN None

Category Wastewater Treatment

MATCH % NONE

TIF DISTRICT None

Priority Essential (2)

Description This project would extend the 30-inch sanitary sewer pipe along Abbey Lane from Burry Drive to the west side of US Highway 218. Total Project Cost: $2,425,000

Status Active

Justification This project will allow development within the watershed west of US Highway 218 and south of Rohret Road.

Expenditures

Total

2021

2022

2023

2024

2025

PLANNING/DESIGN

250,000

250,000

LAND/ROW ACQUISITION

325,000

325,000

CONSTRUCTION

1,650,000

1,650,000

INSPECTION

100,000

100,000

ADMINISTRATION

100,000

100,000

250,000

2,175,000

2,425,000

Total

Funding Sources REVENUE BONDS

Total

2021

2022

2023

2024

2025

2,425,000

2,425,000

2,425,000

2,425,000

Total

Budget Impact/Other This will bring additional revenue along with additional maintenance costs. The estimated maintenance costs are less than $10,000 per year. The estimated amount of additional revenue is unknown. This serves as a declaration of official intent under Treasury Regulation 1.150-2 that it is reasonably expected that capital expenditures will be made in respect of the above-described project, such expenditures to be advanced from the Wastewater fund, and the City reasonably expects to reimburse all or a portion of the expenditures with the proceeds of bonds, notes or other indebtedness to be issued or incurred by the City in the future.

579