FY2022

Contact Kevin Slutts Department PUBLIC WORKS

W3318

Project #

Project Name GSR Generator Enclosure Replacement

Type One Phase

Useful Life 20 years

GRANTEE NONE

PLAN None

Category Water Operations

MATCH % NONE

TIF DISTRICT None

Priority Essential (2)

Description Replace the metal housings enclosing the ground storage reservoir (GSR) back up power generators at the Rochester, Sycamore, and Emerald GSR's. Justification The ground storage reserviors (GSR's) are provided with backup power generation by diesel generators. These generators are external to the building and enclosed within metal housings. These housings have deteriorated and are beginning to allow the weather to damage internal components. Total Project Cost: $40,000 Status Active

Expenditures CONSTRUCTION

Total

2021

2022

2023

2024

2025

40,000

40,000

40,000

40,000

Total

Funding Sources

Total

2021

2022

2023

2024

2025

WATER FUND

40,000

40,000

40,000

40,000

Total

Budget Impact/Other Reduced operational costs associated with annual generator preventative maintenance contract costs. Estimated annual savings is less than $10,000 per year.

Contact Kevin Slutts Department PUBLIC WORKS

W3319

Project #

Project Name Chemical Room & Outdoor Lighting Upgrade

Type One Phase

Useful Life 30 Years

GRANTEE NONE

PLAN None

Category Water Operations

MATCH % NONE

TIF DISTRICT None

Priority Efficiency Improvement (3)

Description Replace the lighting in the water plant chemical rooms and perimeter lights with high efficiency, long life, LED lights and mount the new fixtures in locations more conducive to providing work area illumination and access for preventative maintenance or grounds maintenance activities. Justification The lighting in the chemical rooms at the water plant has issues with illumination and placement. Some lighting was installed in a manner that blocks the fixture from providing the needed light for employees to adequately see the work they are performing. The chemical room lighting bulbs are difficult to replace and require staff to take a number of safety measures up to and including renting scaffolding to replace. Other lights are installed in areas that cannot be reached without renting special equipment or are adversely impacted by the chemicals in the room. The 22 outdoor perimeter lights are short lived (~2 months) and cost about $10 per replacement. Total Project Cost: $100,000 Status Active

Expenditures

Total

2021

2022

2023

2024

2025

PLANNING/DESIGN CONSTRUCTION

10,000

10,000

90,000

90,000

100,000

100,000

Total

Funding Sources

Total

2021

2022

2023

2024

2025

WATER FUND

100,000

100,000

100,000

100,000

Total

Budget Impact/Other The annual bulb replacement cost for the chemical rooms is approximately $1,200. The outdoor lights are short-lived (~2 months) for the cost of the replacement bulbs (~$10/bulb). Total annual bulb replacement expenditure is approximately $1,100. Therefore the operating budget will see an annual savings of $2,300 as well as savings in personnel safety and time.

600