FY2022

Contact Kevin Slutts Department PUBLIC WORKS

W3316

Project #

Project Name Chlorine Feeder System Upgrade

Type One Phase

Useful Life 20 years

GRANTEE NONE

PLAN None

Category Water Operations

MATCH % NONE

TIF DISTRICT None

Priority Essential (2)

Description Design and install new chlorine feed equipment with associated computer system integration and repairs to the CSI Scrubber system. Total Project Cost: $115,000

Status Active

Justification The existing automatic chlorine feeders are reaching their designed end-of-life and are no longer supported by the manufacturer. Updating the system components with current models will allow for more precise control of the chlorine feed system and reduce maintenance time.

Expenditures

Total

2021

2022

2023

2024

2025

PLANNING/DESIGN CONSTRUCTION

15,000

15,000

100,000

100,000

115,000

115,000

Total

Funding Sources

Total

2021

2022

2023

2024

2025

WATER FUND

115,000

115,000

115,000

115,000

Total

Budget Impact/Other Reduced maintenance time and spare parts load - return-on-investment in approximately 8 years. The chlorine system is a high hazard system that includes a number of process controls to keep City staff and the surrounding area safe from a release of chemical.

Contact Kevin Slutts Department PUBLIC WORKS

W3317

Project #

Project Name Water Front Meeting Room A/V Upgrades

Type One Phase

Useful Life 20 years

GRANTEE NONE

PLAN None

Category Water Operations

MATCH % NONE

TIF DISTRICT None

Priority Efficiency Improvement (3)

Description Upgrade the audio and visual equipment in the Water Front Meeting Room with new flat panel screens, associated computer controls, and audio for the use by City Staff to conduct training events and meetings. Upgrade room lighting with LED lights. Justification The Water Front Meeting Room has two broken overhead screens, no mounted projector, and an antiquated audio system. The room was originally designed to be able to host two separate meetings, but has since been adapted to use a large front projector screen that impedes the use of the divider wall and a projector set upon a collapsable table in the middle of the aisle. This setup has proved to be adequate and cumbersome. The goal is to update the room to include better room usage and data display functionality. Total Project Cost: $45,000 Status Active

Expenditures

Total

2021

2022

2023

2024

2025

PLANNING/DESIGN

5,000

5,000

EQUIPMENT

40,000

40,000

45,000

45,000

Total

Funding Sources

Total

2021

2022

2023

2024

2025

WATER FUND

45,000

45,000

45,000

45,000

Total

Budget Impact/Other The operational budget will be impacted by increased internal service chargebacks for the ITS equipment program. Estimated annual impact is less than $5,000 per year.

599

Made with FlippingBook flipbook maker