Contact Kevin Slutts Department PUBLIC WORKS

W3314

Project #

Project Name High Service Pump VFD Replacement

Type One Phase

Useful Life 20 years

GRANTEE NONE

PLAN None

Category Water Operations

MATCH % NONE

TIF DISTRICT None

Priority Essential (2)

Total Project Cost: $650,000

Description Replace the (4) four variable frequency drives (VFDs) on our high service pumps.

Status Active

Justification The VFD's servicing our high service pumps will have been in operation for approximately 21 years when this project reaches construction. This is a typical life span for VFD's. The VFD's have begun to show signs of deterioration with the loss of communications due to worn electronics components and the new SCADA system was modified to accommodate the out-moded communications protocols utilized by these drives. We anticipate continued and more frequent repair activities as these drives reach the end of their useful life.

Expenditures

Total

2021

2022

2023

2024

2025

PLANNING/DESIGN CONSTRUCTION

50,000

50,000

600,000

600,000

50,000

600,000

650,000

Total

Funding Sources

Total

2021

2022

2023

2024

2025

WATER FUND

50,000

600,000

650,000

50,000

600,000

650,000

Total

Budget Impact/Other Potential cost savings derived from decreased power usage, less wear on the pumps, and less repair or reactive maintenance.

Contact Kevin Slutts Department PUBLIC WORKS

W3315

Project #

Project Name Peninsula Well Field Power Redundancy

Type One Phase

Useful Life 70 years

GRANTEE NONE

PLAN None

Category Water Operations

MATCH % NONE

TIF DISTRICT None

Priority Efficiency Improvement (3)

Description Extend MidAmerican electrical service down Foster Rd to the Peninsula Well Field switchgear set situated to the north of the dog park. Upgrade the switchgear set to allow transfer of source power. Justification Currently the Peninsula Well Field is provided electrical service from Rocky Shore Dr via an aerial electrical feed owned by the City. During flood events or other inclement weather this service is threatened and is single point failure that would cause the treatment plant to loose access to high quality source water until power is restored. Running a second electrical service underground down Foster Rd will mitigate the risk associated with this aerial river crossing. Total Project Cost: $250,000 Status Active

Expenditures CONSTRUCTION

Total

2021

2022

2023

2024

2025

Prior

175,000

175,000

75,000

175,000

175,000

Total

Total

Prior

Funding Sources

Total

2021

2022

2023

2024

2025

WATER FUND

75,000

175,000

175,000

175,000

175,000

Total

Total

Budget Impact/Other The impact to the operating budget is negligible.