Project #

Project Name Hwy 1 (Hawk Ridge to WalMart) Water Main Repl

Type One Phase

Useful Life 70 years

GRANTEE NONE

PLAN None

Category Water Operations

MATCH % NONE

TIF DISTRICT None

Priority Essential (2)

Description Replace approximately 1,600 feet of 12-inch water main (1990 vintage) along Highway 1 from the Hawk Ridge apartments to the north side of Highway 1 across from the WalMart entrance. No service lines are in this area. 12-inch PVC with trenchless installation will be specified to eliminate future corrosion issues due to corrosive soil. A LUST area at 809 Hwy 1 will require ductile iron pipe with nitrile gaskets to be use for the replacement. Due to the corrosive soils, V-Bio polywrap will also be specified and consideration for a cathodic protection system. Justification This water main is situated within corrosive soils and has experienced multiple main breaks. Due to being a transmission main, breaks cause very large pressure losses and disruptions within the distribution system. Replacement of this main with new materials installed to mitigate the corrosive effects of the soils will provide more reliable service to our customers. Total Project Cost: $564,000 Status Active

Expenditures

Total

2021

2022

2023

2024

2025

PLANNING/DESIGN CONSTRUCTION

64,000

64,000

500,000

500,000

64,000

500,000

564,000

Total

Funding Sources

Total

2021

2022

2023

2024

2025

WATER FUND

64,000

500,000

564,000

64,000

500,000

564,000

Total

Budget Impact/Other This project will have a neutral impact on the operating budget as it is the replacement of existing infrastructure.