FY2023 Adopted Budget
PUBLIC WORKS
Department
V3174
Project #
Tim Wilkey
Contact
Project Name Aeration Equipment Improvements
One Phase
Type
20 years
Useful Life
GRANTEE NONE
PLAN None
Wastewater Treatment
Category
MATCH % NONE
TIF DISTRICT None
Efficiency Improvement (3)
Priority
Description Phase 1: Replace the remaining mixers in the aeration trains 1 - 4 with high efficiency mixers matching those placed in Cell 9 of trains 1-4 and replace mixers in the high strength tank. This would be total of 30 mixers. Phase 2: Replace Lamson 300 HP Centrifugal Blower with a High Speed Turbo Blower including any ancillary equipment, pipe modifications and PLC programing. Justification Phase 1: Most of these mixers are original to the 2002/2014 construction and have been rebuilt at least once at a cost of $7,000 to almost $10,000 apiece. They typically operate 24hs/7 days a week when the trains are in service. Replacement with the higher efficiency mixer with lower horsepower will decrease energy usage and continue to reduce our carbon footprint. Estimated cost savings over a 20-year period were estimated to be in excess of $600,000 when all 30 mixers in operation. Phase 2: The existing Lamson Blowers were placed in service in 2002 as part of the first iteration of the activated sludge process units. The blower is a "starts across the line", meaning that it's either on or off and cannot be regulated with Variable frequency drives. Because of this and it's HP capacity, it has high starting amps that affect our electrical peak loading billing with REC. The New High Speed turbo blower uses a VFD which eliminates the inrush of power, allowing us to regulate our peak loading and work at a lower operating amperage. Total Project Cost: $3,506,000 Status Active
Future
Expenditures
Total
2022
2023
2024
2025
2026
1,470,000
PLANNING/DESIGN
10,000
10,000
CONSTRUCTION
2,000,000
2,000,000
Total
INSPECTION
4,000
4,000
ADMINISTRATION
2,000
2,000
CONTINGENCY
20,000
20,000
2,036,000
2,036,000
Total
Future
Funding Sources
Total
2022
2023
2024
2025
2026
1,470,000
WASTEWATER FUND
2,036,000
2,036,000
2,036,000
2,036,000
Total
Total
Budget Impact/Other By replacing the Lamson blower with a high speed turbo blower, we anticipate a 10% reduction in power cost for the foreseeable future. The estimated annual savings is less than $10,000 per year.
620
Made with FlippingBook - Online Brochure Maker