FY2023 Adopted Budget

TRANSPORTATION SERVIC

Department

T3027

Project #

Darian Nagle-Gamm

Contact

Project Name Parking Ramp Stairwell Roof Replacement

One Phase

Type

40 Years

Useful Life

GRANTEE NONE

PLAN None

Parking Operations

Category

MATCH % NONE

TIF DISTRICT None

Critical (1)

Priority

Description Repair/replacement of the stairwell rooftops for the Capitol Street Ramp and Dubuque Street Ramp. Total Project Cost: $50,000

Active

Status

Justification The roofs of two stairwells located at the Capitol Street Parking Ramp and the two stairwells at the Dubuque Street Parking Ramp need repaired or replaced. These have reached the end of their useful life and will begin to cause structure damaged if not addressed.

Expenditures

Total

2022

2023

2024

2025

2026

PLANNING/DESIGN

10,000

10,000

CONSTRUCTION

40,000

40,000

50,000

50,000

Total

Funding Sources

Total

2022

2023

2024

2025

2026

PARKING FUND

50,000

50,000

50,000

50,000

Total

Budget Impact/Other This project will greatly reduce future structural maintenance and repair costs. The impact on the current operating budget is a reduction of expenditures due to decreased repair and maintenance costs. The estimated decrease in operating expendtires is less than $15,000 per year.

TRANSPORTATION SERVIC

Department

T3028

Project #

Darian Nagle-Gamm

Contact

Project Name Tower Place Office Remodel

One Phase

Type

20 years

Useful Life

GRANTEE NONE

PLAN None

Parking Operations

Category

MATCH % NONE

TIF DISTRICT None

Efficiency Improvement (3)

Priority

Description Design and remodel of Customer Service and Administrative Support office areas of the Tower Place parking ramp. Total Project Cost: $132,000

Active

Status

Justification Administrative office space demand has greatly changed at our Tower Place location. This remodel will provide dedicated workspaces for three Customer Services Representatives who currently share two work stations in an open office space. The remodel will also provide dedicated office space for Supervisory staff including Operations Supervisors, Director, Associate Director, and a Data Analyst. Currently the Supervisory staff operate in an open workspace room with very limited privacy. Upgraded funiture will also be part of this project.

Expenditures

Total

2022

2023

2024

2025

2026

PLANNING/DESIGN

12,000

12,000

CONSTRUCTION

120,000

120,000

132,000

132,000

Total

Funding Sources

Total

2022

2023

2024

2025

2026

PARKING FUND

132,000

132,000

132,000

132,000

Total

Budget Impact/Other There is no anticipated impact to the operating budget.

642

Made with FlippingBook - Online Brochure Maker