FY2024 Proposed Budget
Capital Improvement Plan 2023-2027 City of Iowa City, Iowa
2023 2027 thru
Department PUBLIC WORKS
Contact Jonathan Durst
Type One Phase
W3325
Project #
Useful Life 20 years
Project Name Roof Replacements
Category Water Operations
Priority Essential (2)
MATCH % NONE GRANTEE NONE
TIF DISTRICT None PLAN None
Status Active
Description Replace the roofs on the Water Plant garage, chemical storage rooms, 5 collector wells, 3 deep wells, and emergency generator building. Total Project Cost: $600,000
Justification The existing roofs are showing signs of failure due to age. The roof material is degrading causing leaks inside the buildings. The roofs will need replacement.
Expenditures
Total
2023
2024
2025
2026
2027
100,000 500,000 600,000
100,000 500,000 600,000
PLANNING/DESIGN CONSTRUCTION
Total
Funding Sources
Total
2023
2024
2025
2026
2027
600,000 600,000
600,000 600,000
WATER FUND
Total
Budget Impact/Other The operating impact of these improvements will be negligible.