FY2024 Proposed Budget

Capital Improvement Plan 2023-2027 City of Iowa City, Iowa

2023 2027 thru

Department PUBLIC WORKS

Contact Jonathan Durst

Type One Phase

W3330

Project #

Useful Life 30 Years

Project Name Water Plant Flowemeter Replacement

Category Water Operations

Priority Critical (1)

MATCH % NONE GRANTEE NONE

TIF DISTRICT None PLAN None

Status Active

Description Part of Unfunded Project #84. Replacement of (1) 12-inch, (2) 20-inch, (3) 30-inch, and (2) 36-inch magnetic flow meters at the Water Treatment Plant. Total Project Cost: $550,000

Justification Flow meters are used to control unit operations of the water treatment system. Magnetic flowmeters are currently installed to control the softeners, chlorine contact tanks, and high service pumps to the Emerald, Rochester, and Plant Service Water transmission lines. The existing magnetic flowmeters are at end-of-life and are malfunctioning. Operations and maintenance teams have developed work around to avoid the costly replacements. These work arounds are beginning to fail as well. Therefore replacement is necessary with new equipment more applicable to the application.

Expenditures

Total

2023

2024

2025

2026

2027

50,000 500,000 550,000

50,000 500,000 550,000

PLANNING/DESIGN CONSTRUCTION

Total

Funding Sources

Total

2023

2024

2025

2026

2027

550,000 550,000

550,000 550,000

WATER FUND

Total

Budget Impact/Other This project will have a neutral impact on the operating budget as it is the replacement of existing infrastructure.