FY25 Proposed Budget

2024 2028 thru

Capital Improvement Plan 2024-2028 City of Iowa City, Iowa

PUBLIC WORKS

Department

Contact Jonathan Durst

One Phase

Type

W3332

Project #

40 Years

Useful Life

Project Name Peninsual Well Field Antenna

Water Operations

Category

GRANTEE NONE

PLAN None

Efficiency Improvement (3)

Priority

MATCH % NONE

TIF DISTRICT None

Active

Status

Total Project Cost: $200,000

Description Install a new antenna at the Rocky Shore Dr. lift station by Crandic Park and decommission the antenna at the N. Dodge St. HyVee.

Justification The Peninsula Well Field is integrated with the Water Treatment Plant SCADA system. The well field communication is via radio to the HyVee antenna and then fiber from the antenna to the Water Plant. Resilient and timely communication with the Peninsula Well Field is necessary to effectively monitor raw water production during all weather events. Both the existing and proposed sites have backup power generation. The installation of reliable fiber to the Rocky Shore Dr. lift station is anticipated to occur with S3958 - Park Rd Reconstruction in 2025.

Expenditures

Total

2024

2025

2026

2027

2028

PLANNING/DESIGN

40,000

40,000

CONSTRUCTION

160,000

160,000

200,000

200,000

Total

Funding Sources

Total

2024

2025

2026

2027

2028

WATER FUND

200,000

200,000

200,000

200,000

Total

Budget Impact/Other This project will have a neutral impact on the operating budget as it is the replacement of existing infrastructure.