Contact Tim Wilkey Depar tment PUBLIC WORKS
V3167
Pr oject #
Pr oject Name Replace Gr it Classifier s
Type One Phase
Useful Life 20 years
MATCH % NONE GRANTEE NONE
TIF DISTRICT None PLAN None
Categor y Wastewater Treatment
Pr ior ity Essential (2)
Description Replace the Grit Classifiers located in the Grit Building including any required piping and bunker modifications. Project includes installing a bagging system and roll-off to move away from having to install a liming system to meet IDNR grit disposal requirements. This cost includes the 2 roll-off containers. Justification The grit classifiers were installed in 2002 and have requiried a major frame repair in 2015 and multiple rotating parts replacment over the past 5 years. The equipment is at the end of it's useful design life. IDNR rules require raising the grit pH to 12 for 2 hours, by installing a bagging system and roll-off, we can apply for a waiver for liming and the roll-off will reduce staff handling the grit. With improvements in technology, the new classifiers are more effective at dewatering and will produce a drier grit. Total Pr oject Cost: $394,000 Status Active
Expenditur es
Total
2022
2023
2024
2025
2026
30,000 325,000
30,000 325,000
PLANNING/DESIGN CONSTRUCTION
6,000 3,000
6,000 3,000
INSPECTION
ADMINISTRATION CONTINGENCY
30,000 394,000
30,000 394,000
Total
Funding Sour ces WASTEWATER FUND
Total
2022
2023
2024
2025
2026
394,000 394,000
394,000 394,000
Total
Budget Impact/Other Grit removal is critical in WWTP operations in meeting its NPDES permit and reduces wear and tear on down steam pumping. Scheduled replacement is is more cost ffective than an emergency replacement project. This project repairs existing equipment which should reduce maintenance and repairs costs. The estimated impact on the operating budget is less than $10,000.