2022-2026 Capital Improvement Program.pdf
Contact Darian Nagle-Gamm Depar tment TRANSPORTATION SERVIC
T3055
Pr oject #
Pr oject Name Tr ansit Maintenance Facility Relocation
Type One Phase
Useful Life 40 Years
MATCH % 20% GRANTEE FTA
PLAN Transportation Plan
Categor y Transit Operations
TIF DISTRICT None
Pr ior ity Essential (2)
Description This project involves the construction of a new transit facility for maintenance operations and storage. As part of this project, the storage area will be expanded allowing for an increase in fleet size and the maintenance facility will be upgraded. The relocation will address the environmental issues that exist at the current facility and allow for the redevelopment of a major commercial site at the corner of Highway 6 and Riverside Drive. Justification The current tranist maintenance facility has outlived its useful life and is in need of replacement. The facility has structural issues from the surrounding area, and a new facility will improve the delivery of service. The new facility would be eventually be consolidated with Equipment Services into one facility to better utilize space and be more cost effective. Grants are being sought to assist in the construction. Total Pr oject Cost: $20,200,000 Status Active
Expenditur es CONSTRUCTION
Total
2022
2023
2024
2025
2026
Pr ior
20,000,000 20,000,000
20,000,000 20,000,000
200,000
Total
Total
Pr ior
Funding Sour ces FEDERAL GRANTS
Total
2022
2023
2024
2025
2026
200,000
15,000,000 5,000,000 20,000,000
15,000,000 5,000,000 20,000,000
TRANSIT FUND
Total
Total
Budget Impact/Other The replacement of transit maintenance facility should be to a newer and more energy efficient facility, however, the new facility will be larger and contain more operational functionality. The additional size and capability of the facility will most likely offset the potential savings from a newer and more efficient facility. Additional savings/cost from this facility has not been determined.