2022-2026 Capital Improvement Program.pdf

Contact Juli Seydell-Johnson Depar tment PARKS & RECREATION

R4229

Pr oject #

Pr oject Name City Par k Pool Replacement

Type One Phase

Useful Life 40 Years Categor y Recreation

MATCH % NONE GRANTEE NONE

PLAN Recreation Master Plan

TIF DISTRICT None

Pr ior ity Efficiency Improvement (3)

Total Pr oject Cost: $6,000,000

Description Replace City Park Pool with new outdoor swimming pool and bathhouse.

Status Active

Justification City Park Pool is an Iowa City landmark and tradition. However, due to its advancing age it will need to be replaced with a more modern facility.

Expenditur es

Total

2022

2023

2024

2025

2026

500,000

500,000

PLANNING/DESIGN CONSTRUCTION

5,000,000

5,000,000

500,000

500,000

CONTINGENCY

500,000

5,500,000

6,000,000

Total

Funding Sour ces

Total

2022

2023

2024

2025

2026

500,000

4,800,000

5,300,000

FACILITY REPLACEMENT RESERVE GO BONDS-GENERAL PURPOSE

700,000

700,000

500,000

5,500,000

6,000,000

Total

Budget Impact/Other This project will increase annual operating expenditures for insurance and utilities, but will also require lower maintenance and upkeep. The net increase in operating expenditures is estimated between $15,000 and $25,000 per year. This serves as a declaration of official intent under Treasury Regulation 1.150-2 that it is reasonably expected that capital expenditures will be made in respect of the above-described project, such expenditures to be advanced from the Capital Projects fund, and the City reasonably expects to reimburse all or a portion of the expenditures with the proceeds of bonds, notes or other indebtedness to be issued or incurred by the City in the future.