2022-2026 Capital Improvement Program.pdf

Contact Jen Jordan Depar tment PUBLIC WORKS

L3338

Pr oject #

Pr oject Name Futur e Landfill Cell

Type One Phase

Useful Life 10 years Categor y Landfill

MATCH % NONE GRANTEE NONE

TIF DISTRICT None PLAN None

Pr ior ity Critical (1)

Description This project includes the preliminary design and studies, detailed design, construction, construction observation, and regulatory compliance associated with implementing the next landfill cell. Justification The current rate of landfilling and compaction allows for approximately 2-3 years in the current cell, Cell FY18. New cells take 2-3 years to design, construct, permit, and complete the initial landfilling. Total Pr oject Cost: $4,400,000 Status Active

Expenditur es

Total

2022

2023

2024

2025

2026

Pr ior

200,000

100,000

300,000

PLANNING/DESIGN CONSTRUCTION ADMINISTRATION

100,000

3,600,000

3,600,000

Total

15,000

25,000 360,000

40,000 360,000

CONTINGENCY

215,000

4,085,000

4,300,000

Total

Pr ior

Funding Sour ces

Total

2022

2023

2024

2025

2026

100,000

215,000

4,085,000

4,300,000

LANDFILL REPLACEMENT RESERVE

Total

215,000

4,085,000

4,300,000

Total

Budget Impact/Other Expediting this project will reduce rock purchases, because operations will allow for using existing interior roads and rainy day pads instead of building new. The annual estimated reduction of expenditures is $25,000 per year.