FY2023 Adopted Budget

PUBLIC WORKS

Department

V3164

Project #

Tim Wilkey

Contact

Project Name Return Activated Sludge Pump Replacement

Multi-Phase

Type

20 years

Useful Life

GRANTEE NONE

PLAN None

Wastewater Treatment

Category

MATCH % NONE

TIF DISTRICT None

Essential (2)

Priority

Description The project would include the replacement of return activated sludge pumps. This includes all pumps and any piping/structural modifications required to fit the pumps. Justification These pumps have been in service since 2002 and are nearing the end of their useful working life. The maintenance repair frequency for these pumps has been increasing in the past year. Failure to replace these pumps in a timely manner could cause diminished operation and treatment of the wastewater resulting in violations of our NPDES discharge permit. Total Project Cost: $1,009,000 Status Active

Expenditures

Total

2022

2023

2024

2025

2026

PLANNING/DESIGN

80,000

80,000

CONSTRUCTION

823,000

823,000

INSPECTION

16,000

16,000

ADMINISTRATION

8,000

8,000

CONTINGENCY

82,000

82,000

1,009,000

1,009,000

Total

Funding Sources

Total

2022

2023

2024

2025

2026

WASTEWATER FUND

1,009,000

1,009,000

1,009,000

1,009,000

Total

Budget Impact/Other New pumps would increase pump efficiency, but lower energy consumption and maintenance costs. The estimated reduction in operating expenditures is less than $10,000 per year.