Final FY25 Adopted Budget

2024 2028 thru

Capital Improvement Plan 2024-2028 City of Iowa City, Iowa

PUBLIC WORKS

Department

Contact Tim Wilkey

One Phase

Type

V3174

Project #

25 years

Useful Life

Project Name Aeration Equipment Improvements

Wastewater Treatment

Category

GRANTEE NONE

PLAN None

Efficiency Improvement (3)

Priority

MATCH % NONE

TIF DISTRICT None

Active

Status

Total Project Cost: $3,628,000

Description Replace the remaining mixers in the aeration trains 1 - 4 with high efficiency mixers matching those placed in Cell 9 of trains 1-4 and replace mixers in the high strength tank. This would be total of 30 mixers.

Justification Most of these mixers are original to the 2002/2014 construction and have been rebuilt at least once at a cost of $7,000 to almost $10,000 a piece. They typically operate 24hs/7 days a week when the trains are in service. Replacement with the higher efficiency mixer with lower horsepower will decrease energy usage and continue to reduce our carbon footprint. Estimated cost savings over a 20-year period were estimated to be in excess of $600,000 when all 30 mixers in operation.

Expenditures

Total

Future

2024

2025

2026

2027

2028

CONSTRUCTION

300,000

350,000

100,000

750,000

2,878,000

300,000

350,000

100,000

750,000

Total

Total

Funding Sources

Total

Future

2024

2025

2026

2027

2028

WASTEWATER FUND

300,000

350,000

100,000

750,000

2,878,000

300,000

350,000

100,000

750,000

Total

Total

Budget Impact/Other We anticipate an energy consumption reduction of 15% and will reduce our electrical usage/cost and continue to reduce our carbon footprint.