Contact Jonathan Durst Depar tment PUBLIC WORKS
W3321
Pr oject #
Pr oject Name Tr eatment Technology Study
Type Multi-Phase
Useful Life 10 years
MATCH % NONE GRANTEE NONE
TIF DISTRICT None PLAN None
Categor y Water Operations
Pr ior ity Essential (2)
Description An engineering study of dissolved nutrient removal from source water (nitrates, polyfluoroalkyl compounds, mycrositins, etc...), the long-term financial and environmental sustainability of lime softening, and filter system valving and build-out based on the study results. Justification Regulations on dissolved ions in source and finished water are changing with federal administrations and increasing evidence of chemcial toxicity which will result in a need to have treatment technologies capable of ionic removal. Further quicklime and lime solids management costs have continued to increase yearly and a cost/benefite analysis of lime softening is warranted while investigating treatment technologies. The filters may need modification to accommodate new technologies. This is a study and will inform future CIP, including five projects on the unfunded list - Nutrient Removal, WTP Filter #6 Buildout, Water Plant Softener Improvements, Soda Ash Replacement, and Lime Lagoon Outlet Structure Modifications. Total Pr oject Cost: $150,000 Status Active
Expenditur es
Total
2022
2023
2024
2025
2026
150,000 150,000
150,000 150,000
PLANNING/DESIGN
Total
Funding Sour ces
Total
2022
2023
2024
2025
2026
150,000 150,000
150,000 150,000
WATER FUND
Total
Budget Impact/Other The impact on the operating budget will be negligible.